Construction Progress Update as of April 10, 2026
Text description of table
Overview
The table describes the progress of the construction phase.
Values
There are four columns:
- Year
- Description
- Progress Bar
- Notes
Row 1:
- Year: 2026
- Description: Initiation
- Progress Bar: 100%
- Notes: Preparatory Works include: Sign Installation
Row 2:
- Year: 2026
- Description: Stage 4
Row 3:
- Year: 2026
- Description: Staging Works
- Progress Bar: 85%
Row 4:
- Year: 2026
- Description: HWY 401 Works
- Progress Bar: 17%
Row 5:
- Year: 2026
- Description: Highbury Stage 1
- Progress Bar: 80%
Row 6:
- Year: 2026
- Description: Highbury Stage 2/li>
- Progress Bar: 5%
Row 7:
- Year: 2026
- Description: —
- Progress Bar: 0%
Presentation
The data is presented in a table. The Progress Bar column uses blue progress bars in each row, with the table cell representing 100% of the progress bar. A 25% filled progress bar will fill 25% of the cell. The progress bar cells also include text stating the percentage.
“Stage 4” is a subheading for the rows below. It has a green background across the row.