Construction Progress Update as of Jan 30, 2026

Text description of table

Overview

The table describes the progress of the construction phase as of Jan 30, 2026.

Values

There are four columns:

  1. Year
  2. Description
  3. Progress Bar
  4. Notes

Row 1:

  • Year: 2026
  • Description: Initiation
  • Progress Bar: 0%
  • Notes: Preparatory Works includes: Sign Installation

Row 2:

  • Year: 2026
  • Description: Stage 4
  • Progress Bar: 0%

Row 3:

  • Year: 2026
  • Description: Staging Works
  • Progress Bar: 0%

Row 4:

  • Year: 2026
  • Description: HWY 401 Works
  • Progress Bar: 0%

Row 5:

  • Year: 2026
  • Description: Highbury Stage 1
  • Progress Bar: 75%

Row 6:

  • Year: 2026
  • Description: Highbury Stage 2/li>
  • Progress Bar: 0%

Row 7:

  • Year: 2026
  • Description: —
  • Progress Bar: 0%

Presentation

The data is presented in a table. The Progress Bar column uses blue progress bars in each row, with the table cell representing 100% of the progress bar. A 25% filled progress bar will fill 25% of the cell. The progress bar cells also include text stating the percentage.

“Stage 4” is a subheading for the rows below. It has a green background across the row.